Works currently in progress :

At air conditioning systems

1. Preparation of cooling towers for cooling season

  • Dismantling, chemical cleaning and fixing systems for spraying and nozzles. If necessary, design of new nozzles and filling those missing
  • Disassembly, cleaning PVC fill of cooling towers (honeycomb) and refitting or replacement of PVC fill filled with lime stones with new PVC fill
  • Washing of baths and tower walls and and repairing damages to the baths and walls
  • Acid cleaning of drop eliminators and air distributers
  • Putting into operation of equipment for water softening, treatment of water by inhibitors and biocide and control of water and sludge removal,
  • If necessary acid washing of the complete cooling installation

2. Preparing of the cooling parts of the chiller for cooling season

  • Chemical and / or mechanical cleaning of the water side of the chiller evaporator and condenser
  • Chemical cleaning of the water-air exchanger in the air conditioning chambers from water and air sides

At ammonia refrigeration system

1. Preparation of evaporative condensers

  • Dismantling, chemical cleaning and fixing systems for spraying and nozzles. If necessary, design of new nozzles and filling those missing
  • Acid washing of the tube bundle by inhibited acid solution, walls and baths of ammonia towers

2. Preparation of water-cooled compressors

  • Chemical flushing of oil cooler
  • Chemical flushing of compressor heads -cooled by water.
  • If necessary, rinsing of the entire distribution installation.